A mobile application project is halfway through development. The team reaches a stabilized velocity after 8 iterations. The sprint duration is two weeks and requirements assigned by the product owner are not changing frequently.
What is the estimated time remaining for the project?

The project is halfway through development.
The team has reached a stable velocity after 8 iterations.
Each sprint duration is two weeks.
Since the project is halfway completed, an equal amount of work remains.
If 8 iterations have been completed, 8 more iterations are required to complete the project.
Each iteration (sprint) lasts 2 weeks.
8 iterations × 2 weeks per iteration = 16 weeks.
16 weeks = 4 months.