A company is planning to launch a new service to improve the customer checkout experience.

A company is planning to launch a new service to improve the customer checkout experience. What should the project manager do to meet the objective of reducing time to market to gain a competitive advantage in the industry?

A.

Engage the project stakeholders to assess the best practices to apply and plan the deliverables before implementation.

B.

Recommend an agile delivery approach and provide information to the stakeholders on agile values and principles.

C.

Educate the team about scrum and ensure that all members are aligned to the roles required.

D.

Consult executive leadership for the most appropriate method for delivery using existing organizational practices.

PMI-200 PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now PMI-200 pdf
Get 65% Discount on All Products, Use Coupon: "ac4s65"