PMI PMI-100 Question Answer
Which technique helps to determine the risks that have the most potential impact on a project?
Cost risk simulation analysis
Expected monetary value analysis
Modeling and simulation
Sensitivity analysis
TESTED 13 Jul 2025
Copyright © 2014-2025 ACE4Sure. All Rights Reserved