PMI PMI-100 Question Answer
Scope, schedule, and cost parameters are integrated in the:
Performance measurement baseline.
Analysis of project forecasts,
Summary of changes approved in a period,
Analysis of past performance.
TESTED 22 Feb 2026
Copyright © 2014-2026 ACE4Sure. All Rights Reserved