PMI PMI-100 Question Answer
In a project, total float measures the:
Ability to shuffle schedule activities to lessen the duration of the project.
Amount of time an activity can be extended or delayed without altering the project finish date.
Cost expended to restore order to the project schedule after crashing the schedule.
Estimate of the total resources needed for the project after performing a forward pass.