Which group is formally chartered and responsible for reviewing, evaluating, approving, delaying, or rejecting changes...

Which group is formally chartered and responsible for reviewing, evaluating, approving, delaying, or rejecting changes to the project and for recording and communicating decisions?

A.

Project team

B.

Focus group

C.

Change control board

D.

Project stakeholders