PMI PMI-100 Question Answer
An input to the Plan Procurement Management process is:
Source selection criteria.
Market research.
A stakeholder register.
A records management system.
TESTED 13 Jul 2025
Copyright © 2014-2025 ACE4Sure. All Rights Reserved