PMI PMI-100 Question Answer
Which of the following is a tool and technique used in the Develop Schedule process?
Three-point estimates
Resource leveling
Precedence diagramming method
Bottom-up estimating
TESTED 13 Jul 2025
Copyright © 2014-2025 ACE4Sure. All Rights Reserved