Summer Special Limited Time 60% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 8w52ceb345

You are the Project Managers of ABC company.

You are the Project Managers of ABC company. The Project team members are from the finance and accounts. The team members report to Finance and Account Managers respectively, and you have limited control over them. What type of organizational hierarchy does ABC company follow?

A.

Matrix organization

B.

Projectized organization

C.

Functional organization

D.

None

PMI-002 PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now PMI-002 pdf
Get 60% Discount on All Products, Use Coupon: "8w52ceb345"