You are the project manager for a Software Development projects.

You are the project manager for a Software Development projects. You are creating a project schedule network diagram for the code development component of the project. This is an example of _________.

A.

Fragment Network

B.

Precedence Diagramming Method [PDM]

C.

Activity On Node [AON]

D.

Arrow Diagramming Method [ADM]