Summer Special Limited Time 60% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 8w52ceb345

You are managing a project that will implement a new MARKETING software package.

You are managing a project that will implement a new MARKETING software package. You have assigned the resources and want to keep the IT manager in the loop by informing him or her of your decisions. Which type of organizational structure are you working in?

A.

Pi'ojectized

B.

Strong Matrix

C.

Weak Matrix

D.

Functional

PMI-002 PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now PMI-002 pdf
Get 60% Discount on All Products, Use Coupon: "8w52ceb345"