Using the PMBOK definition of contingency reserve, which of the following statements about contingency reserves...

Using the PMBOK definition of contingency reserve, which of the following statements about contingency reserves is false?

A.

A contingency reserve is a separately planned quantity used to allow for future situations which may be planned for only in part.

B.

Contingency reserves may be set aside for known unknowns.

C.

Contingency reserves may be set aside for unknown unknowns.

D.

Contingency reserves are normally included in the project's cost and schedule baselines.