A mathematical analysis technique for Develop Schedule
B.
A technique that uses weighted averages to calculate project duration
C.
A technique that uses sequential network logic for schedule
D.
A technique that allows for probabilistic treatment of both network logic and activity duration estimates
The Answer Is:
C
This question includes an explanation.
Explanation:
Critical Path Method (CPM): Calculates a single, deterministic early and late start and finish date for each activity, to be used to determine which activities must be completed on time to avoid impacting the finish date of the project