Resource reallocation from non critical to critical activities is an example of which of the...

Resource reallocation from non critical to critical activities is an example of which of the following Project Scheduling technique:

A.

Resource Leveling

B.

Schedule Compression

C.

Critical Path Method

D.

What if Analysis