PMI PMI-002 Question Answer
Which of the following is output of Direct and Manage Project Execution ?
Change requests.
Responsibility assignment matrix
Work breakdown structure
Project character
Change requests , Deliverables and work performance information is output of Direct and Manage Project Execution.