PMI PMI-002 Question Answer
On any project, who creates the Lessons Learned document?
Customers
Project team
Project sponsor
Stakeholders
The project team contributes to the Lessons Learned document.
TESTED 18 Jan 2026
Copyright © 2014-2026 ACE4Sure. All Rights Reserved