Management reserves are used to handle which type of risk?
A.
Unknown unknowns
B.
Known unknowns
C.
Business risks
D.
Pure risks
The Answer Is:
A
This question includes an explanation.
Explanation:
A is the correct answer. Management reserves are used to handle Unknown unknowns. Specific unknown risks cannot be managed proactively; project team should create a contingency plan.