In project planning, which one of the following is the LEAST applicable to the resource...

In project planning, which one of the following is the LEAST applicable to the resource assignment matrix?

A.

The lines of communication both with in and outside the project

B.

The compensation level of participants

C.

The assignment of responsibilities to the work breakdown stricture

D.

The authority to approve at various completion stages