PMI PMI-002 Question Answer
Dummy relationships or dummy activities can be used in which Sequence Activities technique ?
Arrow Diagramming Method [ADM]
Precedence Diagramming Method [PDM]
Fragment Network
All of the above
TESTED 11 Jul 2025
Copyright © 2014-2025 ACE4Sure. All Rights Reserved