PMI PMI-002 Question Answer
Which of the following can generate a milestone list?
Define Activities
Sequence Activities
Estimate Activity Resources
Estimate Activity Durations
Outputs of Define Activities: Activity list, Activity Attributes and Milestone List. PMBOK Page no 162.
TESTED 11 Jul 2025
Copyright © 2014-2025 ACE4Sure. All Rights Reserved