PMI PMI-002 Question Answer
Which of the following are NOT outputs of the Activity Duration Estimation process?
Activity duration estimates
Schedule baseline
None of the choices are correct
Updates to activity attribute
TESTED 19 Oct 2025
Copyright © 2014-2025 ACE4Sure. All Rights Reserved