After preparing a probability distribution of cost outcomes for a project, the estimate with a...

After preparing a probability distribution of cost outcomes for a project, the estimate with a 20% probability of being exceeded is approximately one standard deviation:

A.

Below the mean.

B.

Above the mean.

C.

Below the median.

D.

Above the median.