Using values such as scope, cost, budget, and duration or measures of scale such as...

Using values such as scope, cost, budget, and duration or measures of scale such as size, weight, and complexity from a previous similar project as the basis for estimating the same parameter or measurement for a current project describes which type of estimating?

A.

Bottom-up

B.

Parametric

C.

Analogous

D.

Three-point