The planned work contained in the lowest level of work breakdown structure (WBS) components is...

The planned work contained in the lowest level of work breakdown structure (WBS) components is known as:

A.

Work packages.

B.

Accepted deliverables.

C.

The WBS dictionary.

D.

The scope baseline.