What is the estimate at completion (EAC) if the budget at completion (BAC) is $100,...

What is the estimate at completion (EAC) if the budget at completion (BAC) is $100, the actual cost (AC) is $50, and the earned value (EV) is $25?

A.

$50

B.

$100

C.

$125

D.

$200