A technique to calculate the theoretical early start and finish dates and late start and finish dates
B.
A schedule network analysis technique that modifies the project schedule to account for limited resources
C.
A schedule compression technique that analyzes cost and schedule trade-offs to determine how to obtain the greatest amount of compression for the least incremental cost
D.
A technique to estimate project duration when there is a limited amount of detailed information about the project
The Answer Is:
B