Which of the following processes are part of the Project Integration Management Knowledge Area?
Develop Project Management Plan, Collect Requirements, Create WBS
Develop Project Management Plan, Control Scope, Develop Schedule
Develop Project Charter, Define Scope, Estimate Costs
Develop Project Charter, Direct and Manage Project Execution, Close Project or Phase