Which process uses occurrence probability and impact on project objectives to assess the priority of...

Which process uses occurrence probability and impact on project objectives to assess the priority of identified risks?

A.

Risk identification

B.

Qualitative risk analysis

C.

Risk management planning

D.

Quantitative risk analysis