PMI PMI-001 Question Answer
Which of the following are three inputs to the risk register?
Risk register updates, stakeholder register, and quality management plan
Communication management plan, enterprise environmental factors, and activity duration estimates
Risk management plan, activity cost estimates, and project documents
Project scope statement, organizational process assets, and scope baseline
TESTED 15 Feb 2026
Copyright © 2014-2026 ACE4Sure. All Rights Reserved