PMI PMI-001 Question Answer
Which of the following is an output of the Define Activities process?
Activity list
Project plan
Activity duration estimates
Project schedule
TESTED 01 Nov 2025
Copyright © 2014-2025 ACE4Sure. All Rights Reserved