CompTIA PK0-005 Question Answer
Functional managers are reluctant to provide a project manager with resources for a project because they think the project should include a certain scope. The project manager reviews the project documentation and confirms the items the functional managers wanted to include were out of scope. Which of the following would be the best course of action for the project manager to take?