During the testing process, testers have found multiple bugs that could jeopardize the project commitment...

During the testing process, testers have found multiple bugs that could jeopardize the project commitment date Which of the following tools should the project manager use first to update the findings?

A.

Defect log

B.

Change log

C.

Issue log

D.

Risk log