During an active project, the finished product is not meeting quality specifications Which of the...

During an active project, the finished product is not meeting quality specifications Which of the following actions should be taken after the project manager determines what would be needed to resolve the issues?

A.

Communicate the change status.

B.

Document change recommendations

C.

Create a change request.

D.

Implement the changes