During a phase review, two stakeholders discuss the approval of a deliverable.

During a phase review, two stakeholders discuss the approval of a deliverable. The project manager convinces the stakeholders to agree on a common solution. Which of the following best describes what the project manager did to gain approval from both stakeholders?

A.

Force

B.

Smooth

C.

Compromise

D.

Avoid