Defects associated with project deliverables have been reported.

Defects associated with project deliverables have been reported. The project team needs to find the cause of the defects. Which of the following tools should the project team use to find the cause?

A.

Kanban board

B.

Pareto chart

C.

Ishikawa diagram

D.

Decision tree