An external developer working on a project at an hourly rate provides an invoice at...

An external developer working on a project at an hourly rate provides an invoice at the end of a month for 80 hours spent on a project. The project manager realizes that there were no tasks assigned to this developer last month. Which of the following actions should the project manager take first?

A.

Consult other developers.

B.

Escalate the issue to the project steering committee.

C.

Request the developer provide justification.

D.

Decline the invoice.