A project manager was not part of a contract negotiation.

A project manager was not part of a contract negotiation. The project manager is concerned that stakeholders will expect the project to achieve deliverables requested in the RFP Which of the following documents should the project manager produce FIRST to start communication about the boundaries of the project?

A.

Milestone chart

B.

Work breakdown structure

C.

Project charter

D.

Detailed scope statement