A project manager operating within a functional organizational structure is trying to avoid a project...

A project manager operating within a functional organizational structure is trying to avoid a project roadblock due to a mobilization fee that has not been paid to a contractor. Which of the following should the project manager do first?

A.

Authorize payment from the contingency budget.

B.

Follow up on the payment request with the payable clerk.

C.

Negotiate with the contractor to be paid later in the project.

D.

Escalate the issue to the financial controller.