A project manager needs to develop a way to control who can modify documents, artifacts, and other data related to the product. Which of the following would be the best way to accomplish this objective?

A.

Define access requirements.

B.

Develop a transition plan.

C.

Create a responsibility assignment matrix.

D.

Create a work breakdown structure.