A data center is under construction, and the project manager wants to address the risks...

A data center is under construction, and the project manager wants to address the risks related to physical injuries. Which of the following is the best risk response method for this scenario?

A.

Avoid injuries by using robots to perform tasks.

B.

Transfer risk to an insurance company.

C.

Mitigate risk by training the construction workers.

D.

Accept the risks inherent to construction.