A critical piece of equipment that is needed for the installation of a point-of-sale solution...

A critical piece of equipment that is needed for the installation of a point-of-sale solution is delayed from the manufacturer. The delay will cause the project to be significantly behind schedule. The project manager decides to buy the item at a higher cost from another vendor who can supply it immediately. Which of the following risk management approaches has the project manager taken?

A.

Mitigate

B.

Transfer

C.

Accept

D.

Share