CompTIA PK0-005 Question Answer
A client provides a project plan to the assigned project manager and suggests that the project manager and team just need to execute the plan. Upon further investigation, the document contains:
• Purpose
• Scope of work
• Location of work
• Period of performance
• Deliverables schedule
• Applicable standards
• Acceptance criteria
• Special requirements
• Payment schedule
Which of the following documents did the client provide to the project manager?