You are the program manager for your organization and are reviewing several proposed change requests...

You are the program manager for your organization and are reviewing several proposed change requests for your program. Mary, a stakeholder, who has made a change request is asking why it is taking you so long to review the change. You tell her that you must perform integrated change control to review each change request. What is integrated change control?

A.

It is the review of the impact of the change on the program's knowledge areas.

B.

It is the review of the impact of the change on the time, cost, scope, and quality baselines.

C.

It is the review of the impact of the change on the program's triple constraints.

D.

It is the review of the impact of the change on the program's Iron Triangle.

PgMP PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now PgMP pdf
Get 65% Discount on All Products, Use Coupon: "ac4s65"