PMI PgMP Question Answer
You are the program manager for your organization. You have created a statement of work, request for proposal, and an invitation to a bidder's conference for 17 possible vendors. During the conference there were QUESTION NO:s about your request for proposal and statement of work that led to clarifications. After the vendor conference you should update what information to send back to the vendors?