Weekend Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: ac4s65

Program A is dependent upon program B to complete benefits sustainment for two benefits.

Program A is dependent upon program B to complete benefits sustainment for two benefits. Program A is on track to meet program benefits. However, program B’s program manager has just advised that program B has been closed.

What should program A’s program manager update and review first with the stakeholders?

A.

Benefits sustainment plan

B.

Benefits register

C.

Benefits management plan

D.

Benefits transition plan

PgMP PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now PgMP pdf
Get 65% Discount on All Products, Use Coupon: "ac4s65"