Program A is dependent upon program B to complete benefits sustainment for two benefits.

Program A is dependent upon program B to complete benefits sustainment for two benefits. Program A is on track to meet program benefits. However, program B’s program manager has just advised that program B has been closed.

What should program A’s program manager update and review first with the stakeholders?

A.

Benefits sustainment plan

B.

Benefits register

C.

Benefits management plan

D.

Benefits transition plan