June is the program manager for her organization.

June is the program manager for her organization. Management has asked June to create a visual mapping of the program scope so that all of the key stakeholders can see all of the elements of the program scope. June needs to create what kind of document to show all of the program deliverables based on the program scope?

A.

Program network diagram

B.

Program benefits mapping chart

C.

Program budget

D.

Program work breakdown structure