Gary is program manager for his organization.

Gary is program manager for his organization. His current program is over budget and is slipping on the program schedule. Management has demanded a change to the program scope. What is the most likely type of change management would make to this program scope?

A.

A change to add additional funds to the program scope

B.

A change to reduce the program scope

C.

Anything that management demands

D.

A change to add additional time to the program schedule