A program manager recognizes that a successful resource being used in project A could also...

A program manager recognizes that a successful resource being used in project A could also be used in project B.

What should the program manager do first to leverage the utilization of this resource?

A.

Assign project A's resource to project B.

B.

Reassign the resource to project B after project A ends.

C.

Prioritize the resource to optimize their use across both projects A and B.

D.

Mitigate risk by leveraging other resources in project A.