A program includes the development and shipping of 12 million product units over the next...

A program includes the development and shipping of 12 million product units over the next year. However, one program supplier has a history of overestimating its planned volume, which puts the product launch at risk.

What should the program manager do to monitor and control the supplier?

A.

Use expert judgment, and update the program procurement plan.

B.

Seek stakeholder approval of program procurement management activities.

C.

Examine performance reports, audits, and inspections.

D.

Review proposal evaluation criteria, risk analyses, and mitigation strategies.