You have just finished a major checkpoint in your portfolio and the portfolio has to...

You have just finished a major checkpoint in your portfolio and the portfolio has to undergo several changes in order to re-align with the strategies. One component of your portfolio has been cancelled and the resources are going to be reallocated to other components. Which process does these activities?

A.

Manage Supply & Demand

B.

Authorize Portfolio

C.

Manage Portfolio Oversight

D.

Optimize Portfolio